Church Renovations

The second phase of our renovation project is set to begin. The renovation period is set to take place from June 1st to October 15th, as follows:

During the months of June and July work will commence on the south end of the parking lot (near Lourdes Lane). This will mean that the south exit of the parking lot will be closed off and parishioners will have to enter and exit off of Earl Street.

During the month of August the entire parking lot will not be available as we will be installing infiltration tanks to hold rain water etc., and the entire parking lot will also be resurfaced and painted. This will mean that parishioners will have to enter and exit the Church by the 2 entrances on Sherbourne Street.

During September and October parishioners will need to use the parking lot entrance and the north entrance on Sherbourne Street as work will be done on the portico on Sherbourne Street.

Please take note of all the signs that will be used in and around the construction sites just as you did last Fall, and please be careful around the construction site. Unfortunately, most of the disruption will be during the month of August as the parking lot will be unavailable. The parish has made arrangements of you who drive Sunday Mass to park at Mgsr. Fraser School on Isabella Street during the renovations should our parking lot be full.

This work on our beautiful church could not be done without your generous assistance to our Capital Campaign. Thank you! And thanks for your patience and cooperation during the renovations!